Construction & FIDIC · 29 September 2026

Dispute Boards under FIDIC 2017: Avoiding Disputes Before They Start

The 2017 FIDIC contracts turned the dispute board into a standing board with a dispute-avoidance role. What changed, and how employers and contractors can use it.

Construction and infrastructure projects generate claims as a matter of course: variations, delay, ground conditions and payment. The question is whether those claims become disputes that halt the work. The 2017 editions of the FIDIC Red, Yellow and Silver Books were written to make that less likely.

From DAB to DAAB

The 1999 FIDIC contracts introduced the Dispute Adjudication Board (DAB). In the 2017 suite it became the Dispute Avoidance/Adjudication Board (DAAB), and the change of name signals a change of purpose. The board is a standing board, appointed at the start of the project, and is expected to help the parties avoid disputes as well as decide them.

The 2017 contracts also split the old Clause 20. Clause 20 now deals with Claims and Clause 21 with Disputes and Arbitration, so a claim that is simply being administered is kept apart from a formal dispute.

Avoidance in practice

Under Sub-Clause 21.3 the parties may jointly ask the DAAB for informal assistance on an issue before it hardens into a dispute. Used well, regular site visits and early, informal discussions with the board can settle technical disagreements in days rather than months.

Adjudication: pay now, argue later

If a formal dispute does arise, it must be referred to the DAAB for a decision before either party can go to arbitration. The decision is binding and must be complied with straight away, even if a party disagrees with it. A party that is dissatisfied must give a Notice of Dissatisfaction within the period the contract sets (28 days after receiving the decision), or the decision becomes final and binding. Amicable settlement is then attempted before arbitration.

Practical points for project teams

  • Appoint the DAAB at the start of the project, not when the first dispute arrives.
  • Keep the board informed with regular project reports and site visits.
  • Track notice periods carefully. Under FIDIC, missing a time limit can cost a party its claim.
  • Treat the board’s informal views as an early warning of how a formal decision would go.

FIDIC describes the referral of disputes to a dispute board as one of its “golden principles”. For employers and contractors in Kenya and across Africa, where FIDIC forms are widely used on public and donor-funded works, making the board work is one of the best investments a project can make.

This article is general information, not legal advice. For advice on a specific matter, please get in touch.